Time, Work & Distance
Basic Numeracy & Data Interpretation · PYQ 2023
A, B, C working independently can do a piece of work in 8, 16 and 12 days respectively. A alone works on Monday, B alone works on Tuesday, C alone works on Wednesday, A alone again works on Thursday and so on. Consider the following statements:
1.The work will be finished on Thursday.
2.The work will be finished in 10 days.
Which of the above statements is/are correct?